By: David Pugliese, Defence Watch
Defence department bureaucrats rejected a plan to outfit the navy’s new supply ship with high-tech guns needed for its protection because they wanted to save money, officials with a Quebec shipyard say.
Davie Shipbuilding is pushing back against recent claims by the Royal Canadian Navy that the Asterix supply vessel it converted for the Canadian Forces can’t go to war.
Company officials point out Asterix can be used in combat as the vessel has been outfitted with similar navigation and other systems that will eventually be installed on a new future fleet of Canadian warships. In addition, the company has acquired insurance coverage for the vessel to operate in high risk and war risk areas, Davie noted in a statement on its website.
The vessel can also be outfitted with weapons, a capability Davie originally proposed to the Department of National Defence. But the installation of high-powered gatling guns – currently in storage in a military depot – was turned down by bureaucrats as a cost-saving measure, Davie sources and industry representatives point out.
“The ship can go wherever the Canadian Armed Forces require it to go,” Davie said on its website in response to questions about whether Asterix can be used in combat.
Naval officers acknowledged at a news conference in late January with Defence Minister Harjit Sajjan at CFB Esquimalt that a number of Phalanx guns are in storage but those are being saved so they can be outfitted on the new Joint Support Ships.
It is unclear when the navy will get those new supply vessels as construction has yet to start. Some estimates put the delivery of the first ship at 2022 but there have been suggestions that vessel could come as late as 2024 or 2025.
The Asterix, which is being leased to the federal government by a sister company to Davie, is being prepared to head to sea in March in support of Royal Canadian Navy operations. It is expected to be at sea for up to six months.
DND did not respond directly to specific questions about why it rejected the installation of Phalanx guns on Asterix.
But Pat Finn, assistant deputy minister for materiel, told a Commons defence committee on Feb. 1 that getting Asterix as quickly as possible was the main focus for the department. He said the Davie supply vessel is different from the Joint Support Ships in terms of its robustness. “We did not impose that upon a commercial ship, because of the speed at which we needed it,” he said. “What it needed to do, what kinds of areas it could go to, and the things it can do are quite different. The Asterix, in the context of that service contract to us, is delivering exactly what we asked of it.”
The ship can go wherever the Canadian Armed Forces require it to go
Davie, however, disputes claims Asterix is not as robust. “Operationally it is able to perform an identical role to that of the potential future Joint Support Ships,” the company added.
The Asterix is also at the heart of federal government’s case against Vice Admiral Mark Norman.
Norman has been accused by the RCMP of warning Davie that Liberal cabinet ministers wanted to derail the Asterix project.
That development leaked out to the news media and the resulting embarrassment forced the Liberal government to back down on its plans and Asterix proceeded. Norman, who was suspended from his job by Chief of the Defence Staff Gen. Jon Vance more than a year ago, has denied any wrongdoing. No charges have been laid against Norman and the claims made against him by the RCMP are so far unproven.
Prime Minister Justin Trudeau has twice predicted that Norman will eventually wind up in court, prompting concerns of political interference and concerns the Liberal government is punishing the officer.
The Canadian Armed Forces (CAF) Dispatch is your one stop for all domestic and international news regarding the CAF. "Mentioned in the Dispatches"
Showing posts with label Federal Fleet Services. Show all posts
Showing posts with label Federal Fleet Services. Show all posts
Tuesday, February 27, 2018
Wednesday, February 7, 2018
MV Asterix (iAOR) Reaches Full Operational Service within RCN
PRESS RELEASE - Davie Shipbulding & Federal Fleet Services
On January 29, 2018, Davie Shipbuilding and Federal Fleet Services announced that following an intensive period of at-sea trials and testing, Asterix has been formally accepted by the Department of National Defence and has now entered full operational service with the Royal Canadian Navy (RCN) and Royal Canadian Air Force (RCAF).
As planned, Asterix performed daily replenishment-at-sea (RAS) exercises with the RCN and conducted extensive RCAF CH-148 Cyclone helicopter operations to prove and demonstrate the world-leading capabilities of the Resolve-Class Naval Support Ship. These exercises have included everything from dual RAS operations to helicopter landing, take-off and vertical replenishment trials.
Spencer Fraser, CEO of Federal Fleet Services commented "To deliver the first Canadian naval ship in over twenty years, the first supply ship in almost 50 years, and to reach FOC so efficiently and in such a short period of time is a testament to the hard work, dedication and dynamism of the teams at Davie and FFS. We are all very proud of our achievement and appreciative of the professional support we have received from DND and PSPC."
Fraser added, "We promised the government that we would fill a strategic gap in an expedited manner, that we would save the Canadian taxpayer money with our solution, and most importantly, that we would provide the men and women of the RCN and RCAF with a world-class capability they could be proud of. Today marks that achievement and we stand ready to assist the Government of Canada to do more."
Alex Vicefield, Chairman of Davie commented, "We would like to thank Prime Minister Trudeau for the confidence and trust he placed in Canada's largest shipbuilder with the award of this program. We are proud to have delivered, as promised, on this vital defence capability which will serve Canada for years to come."
Over 900 Canadian companies from coast-to-coast participated in the build of Asterix, and the Resolve Class has been hailed worldwide for the innovative Canadian solutions integrated onboard. Participation in this project has assisted the exports of many of Davie's Tier 1 sub-contractors; Hepburn of Toronto designed and built the RAS equipment, L3 MAPPS of Montreal designed and installed the Integrated Platform Management System and OSI of Vancouver designed and built the Integrated Bridge System. By participating in the project, these and other innovative Canadian companies have been able to win export opportunities.
Asterix is now ready for global deployment to support combat and humanitarian operations as directed by the Government of Canada.
On January 29, 2018, Davie Shipbuilding and Federal Fleet Services announced that following an intensive period of at-sea trials and testing, Asterix has been formally accepted by the Department of National Defence and has now entered full operational service with the Royal Canadian Navy (RCN) and Royal Canadian Air Force (RCAF).
![]() |
| Asterix completes Royal Canadian Navy trials, achieves Full Operational Capability (FOC) (CNW Group/Davie Shipbuilding) |
![]() |
| Asterix completes Royal Canadian Navy trials, achieves Full Operational Capability (FOC) (CNW Group/Davie Shipbuilding) |
Spencer Fraser, CEO of Federal Fleet Services commented "To deliver the first Canadian naval ship in over twenty years, the first supply ship in almost 50 years, and to reach FOC so efficiently and in such a short period of time is a testament to the hard work, dedication and dynamism of the teams at Davie and FFS. We are all very proud of our achievement and appreciative of the professional support we have received from DND and PSPC."
Fraser added, "We promised the government that we would fill a strategic gap in an expedited manner, that we would save the Canadian taxpayer money with our solution, and most importantly, that we would provide the men and women of the RCN and RCAF with a world-class capability they could be proud of. Today marks that achievement and we stand ready to assist the Government of Canada to do more."
Alex Vicefield, Chairman of Davie commented, "We would like to thank Prime Minister Trudeau for the confidence and trust he placed in Canada's largest shipbuilder with the award of this program. We are proud to have delivered, as promised, on this vital defence capability which will serve Canada for years to come."
Over 900 Canadian companies from coast-to-coast participated in the build of Asterix, and the Resolve Class has been hailed worldwide for the innovative Canadian solutions integrated onboard. Participation in this project has assisted the exports of many of Davie's Tier 1 sub-contractors; Hepburn of Toronto designed and built the RAS equipment, L3 MAPPS of Montreal designed and installed the Integrated Platform Management System and OSI of Vancouver designed and built the Integrated Bridge System. By participating in the project, these and other innovative Canadian companies have been able to win export opportunities.
Asterix is now ready for global deployment to support combat and humanitarian operations as directed by the Government of Canada.
Wednesday, December 13, 2017
Davie Warns about Government’s Lack of action on Shipbuilding
By: David Pugliese, Defence Watch
| The naval support ship Asterix is unveiled at a ceremony at the Davie shipyard in Levis, Que., on July 20, 2017. The Asterix was delivered on time and budget. Something the CSC Fleet Proposal for Bits cannot say. |
Davie Shipbuilding and a number of its Montreal-area suppliers will hold a news conference Thursday to warn about the federal government’s “inaction” on tending shipbuilding contracts and how that will affect jobs.
Spencer Fraser of Davie Shipbuilding will outline the various proposals that the yard has made to the Liberal government (for icebreakers, supply ships, etc) and “present the results these efforts have yielded to date.” (all rejected?).
Politicians and unions in Quebec have been turning up the heat on the Liberal government, questioning why Davie shipyards in the province isn’t getting any more work from the federal government. Davie converted a commercial container ship into a supply vessel for the Royal Canadian Navy. The ship, the Asterix, goes into service early next year and under the agreement will be leased to the RCN. Davie says it is ready to quickly convert another vessel into a supply ship.
But Prime Minister Justin Trudeau’s government has said thanks but no thanks.
Transport Minister, and former navy officer, Marc Garneau said the federal government doesn’t need another supply ship. ”We cannot artificially create a need for something that doesn’t exist,” he told reporters.
Spencer Fraser of Davie Shipbuilding will outline the various proposals that the yard has made to the Liberal government (for icebreakers, supply ships, etc) and “present the results these efforts have yielded to date.” (all rejected?).
Politicians and unions in Quebec have been turning up the heat on the Liberal government, questioning why Davie shipyards in the province isn’t getting any more work from the federal government. Davie converted a commercial container ship into a supply vessel for the Royal Canadian Navy. The ship, the Asterix, goes into service early next year and under the agreement will be leased to the RCN. Davie says it is ready to quickly convert another vessel into a supply ship.
But Prime Minister Justin Trudeau’s government has said thanks but no thanks.
Transport Minister, and former navy officer, Marc Garneau said the federal government doesn’t need another supply ship. ”We cannot artificially create a need for something that doesn’t exist,” he told reporters.
Subscribe to: